Project update: Since I wrote last, we seem to be making progress at the site. Still waiting until the end of this week to get my big shipment of cement, but in the meantime we have found 4 tons locally and two of those have already been made into bricks. We have almost hit water digging the well; should be a few more days. We have all the workers lined up and are following budget for the most part. We have already completed a small shelter. The foundation of each building is already dug, but waiting for cement (nationwide shortage and delays, but we have an order in and it’s promised to arrived end of this week). Sand and gravel shipments are reliable.